RTUG Project ManagementContract ExpansionAnd RTF 2010 Work Plan Budget Adjustments
RTF
March 2, 2010
2
Goal Today
Direction on Scope of Work & Deliverables
Decision on funding additional projectmanagement & research (Phase 4)
Which-Way-istock
3
Refresher:  Phase 3
Monitored data on 174 units in 2009
Promising results & savings methodology
Presented November 2009
Further analysis & development needed for SavingsMethodology, calculator or deemed savings:
Annual metering results
Specifications & protocol
Half dozen other issues to resolve with additional research
Out of funding for RTUG project management
empty-pockets
4
January 2010
RTUG endorsed continuation of the projectmanagement by New Buildings Institute (NBI)
Valuable regional cooperative effort
Sole source basis subject to review of scope
Last RTF Meeting
Preliminary cost estimate Phase 4
>$80K for project & technical management
Raised issue of how to determine going forward
Will it fit in budget?
What other projects might come before RTF?
How to decide in uncertain future?
5
Since Last RTF Meeting
NBI solicited & assembled next-step research
Polled key RTUG participants for ideas
Developed research & analytical path
Draft scope for Phase 4 circulated to the RTUGfor comment
Project management & coordination
Research & analytical scope based on comments
BPA questioning cost-effectiveness
Costs high, unknown persistence
6
Where to from here?
next-steps
steps
7
Next Steps to Get to Savings Methodology
steps
1.Complete collecting & storing the 12-month data
2.Determine confidence in annual savings methodology
3.Further assessment of data:
Baseline & treatment conditions, persistence of fan schedules, annual fanpower & duty cycle, negative savings, isolate refrig & air flowconditions, TMY vs site temps, service tech interviews
4.Develop scope & budget for extending to 36-month monitor
5.Establish functioning data repository with open access
Direct Research Funded by BPA via Cadmus.
Needs RTUG review & technical guidance.
Unfunded Project Management.
8
Revised Scope of Work Phase 4Management ($27K)
Management, Communications & Reporting
3 RTUG & 3 RTF meetings over 9 months
75 hours
Facilitate regional service & field measurementprotocols, encourage added M&V & sampling
75 hours
Communicate & collaborate with other regions
30 hours
Meeting minutes, reports, presentations, final report
9
Revised Scope of Work Phase 4Technical ($21K)
Review results of analysis by BPA/Cadmus, synthesize fordiscussion at RTUG & presentation to RTF
Develop the complete savings methodology for proposal to the RTF
70 hours
Phase 1 database development assistance
10 hours
Develop elements of strategic plan for RTU next steps
Service vs early replacement, incorporate DCV/Premium Ventilation,VSD/ECM motors, fan upgrade, FDD, Evap Hybrid RTU, AdvancedRTU, digital economizer control, other Emerging Tech
Internet-enabled T-Stats, lower-cost monitoring, whole-buildingapproach to monitoring,
75 hours
10
Summary of Critical Path Costs
Unfunded Management
NBI Project Management
$27K
NBI Technical Management
$21K
NBI Admin & Direct
$  4K
NBI Total
$52K
11
Summary of Potential AdditionalRTU Research Costs
Unfunded Potential Direct Research
Reconcile measured results & simulation modeling.Develop simulation tools (DOE2/eQUEST) thatreflect measured results from study
$20K-$50K
Expected Value Premium Ventilation Analysis
$15K-35K
Extended RTU DDC Sequences & Testing
$15K
Inverse modeling approach vs 2-week pre-post
?
Extending long-term monitoring to 36 months orlonger
?
Test of RTU control Internet performancemonitoring
$100K
Co-funding ASHRAE 1608 RTAR
$20K ?
12
empty-pockets
So Where’s the Money?
13
Budget Snap Shot – March 2010
14
Issues
About $175K budget for “unidentified incoming” forthe remainder 2010
How much of that for RTUG Phase 4?
What other unidentified incoming will show up?
Where to get any remainder for RTUG?
Solicit direct contributions
Find a sugar daddy
Cut the RTUG phase 4 scope & budget
15
Proposal
Allocate $52K of “Available” to RTUG Phase 4 Scope
Sole source to NBI
Final scope to RTF staff working with RTUG
Decide later on RTF support for further RTUG work(2011) or find other funders
Leaves $120K for remainder of 2010 for otherincoming projects