•Meet the May 1, 2010, reporting requirement to the Michigan Legislature.
–Finalizing Investment Grade Traffic Study
–Releasing Request for Proposal of Interest
–Developing Financial Model that will allow the Private Sector to finance the project
•U.S. Property purchases to begin in 2010.*
•U.S. Construction to begin in 2010 (mainly for the interchange).*
•Secure the Presidential Permit in U.S.—2010.
•Secure Required Michigan Legislation in 2010 to:
–Form a Public Private Partnership (P3)
–Allow us to enter into an agreement with Canada
–Allow tolling on the new crossing
•Form the PPP for the Bridge, possibly Plazas—2010.*
•Secure Additional State/Federal Funding--Continuous.
•Business case completed – 2010
•Legal Advisory
* Subject to Michigan legislative approval and funding