Tracking a Project PlanA Case Study
Life Cycle of a Plan
Project Sized
Project Estimated
Project Planned
Budget
Schedule
Project Tracked
Constituents of a Plan
Schedule
Duration by WBS Task
Project Start (or end)
Constraints (Internal/External)
Budget
Assigned Resources to Tasks
Plan
Schedule
+
Budget
=
Plan
Project Plan
Sized
Appropriate Units of Size (SW: KSLOC)
Estimated
Duration
Effort
Scheduled
WBS
Assignment of Resources
Project Tracking and Oversight
Data Collection
Forecasting
Reporting
Eliminate Variances
Taxonomy/Artifacts
Tasks
Resources
Assignments (Task + Resource)
Work
Duration
Summary Tasks (Titles)
Tasks (Imperative Mood and Unique)
Constraints (Internal/External/Calendar)
Data Collection Methods
Using Project Web Access (PWA)
Methods
Hours/day
% Complete*
Total Hours
*Note: “% Complete” NEQ to “% Work Complete”
Chosen Method
Hours/day/Resource
Hours Worked
Remaining Work
Notes (Other data Supplied)
Unplanned/Planned Work interruptions
Unplanned/Planned Delays
Other pertinent information
Data Collection Process
Resource
Using PWA, enters
Hours worked, Remaining Hours
Sends update to PM via PWA*
PM (or representative)
Updates Plan
*Note: Automatic e-mail notification occurs
Forecasting
Computes new Forecast
Publishes update*
*Note: Automatic e-mail notification occurs
Reports Out
Prepares and Distributes Reports*
*Note: Automatic e-mail notification occurs
Elimination of Variances*
Critical Path mandatory; othersvoluntary
Add resources
Change Scope
Change Baseline
*Notes:
Qualified by Criticality
Must eliminate negative schedule variances; positive are voluntary
Must eliminate positive cost variances; negative are voluntary
Add Resources
Reassign
Procure additional
Comes from Reserve or
Requires Change Board Action or
Obtain from Reserve
Change Scope
Change Baseline Duration and/orBaseline Work
Requires Change Board Action if affectsoverall contract cost and/or schedule
Requires Change Board Action ifContracted functionality is changed
Change Baseline*
Cost or Schedule
Cost
Take from Reserve
Reallocate
Schedule
Reduce Slack
Change constraints
*Note:  These changes do not affect the Contract provisions
 aka scope of the contract
Settings for PWA
Resources are in the Resource Pool;i.e. have User Account
PM has Client/Server account on theProject Server
Options set
Method selected
Resource Accounts
Required Windows Authentication
Had e-mail address entered
E-mail server identified in ProjectServer
Hourly cost set
Set to $1, then costs are hours
Project Options
Schedule Options
Calculation Options
Collaborate Options
Save Options
Published Fields
Timesheet View
E-Mail Notification
Schedule Options
Calculation Optons
Collaborate Options
Save Options
Set Published Fields
PWA Tracking Settings (1)
PWA Tracking Settings (2)
Timesheet View
E-Mail Notification
Other Considerations
Server is implemented
Sharepoint is initialized
Permissions are set appropriately
Security is set appropriately
Views are arranged
Server Configuration is set
Other Methods
IPT Lead Reports
Earned Value Methods
Schedule Only
IPT Lead Reports
Make the IPT Lead the Resource onthe Tasks
Set data to be collected:
Start and finish dates only  + RemainingHours/Duration or
Total hours only + Remaining Hours or
% Complete + RemainingHours/Duration
Earned Value Methods
Set Tasks to use “Physical %Complete”
Resources report only Actual Starts,Finishes and Remaining Duration
Schedule Only
Collect only Remaining Duration