STScI Integrated Scheduling System
Bench Timing Testing of Phases 1-5 completed (T. Wheeler)
Essential for SMGT-readiness certification
Target Acquisition FSW component not yet tested
Unique Timing SMS and Reconfiguration SMS-suite
>>FUV and NUV completed successfully
STScI Commanding Certification SMS
>>NUV completed successfully
>>FUV Commanding Certification identified minor issue
Hand-edited SMS ran successfully
>>FUV testing requires FUV detector ETU
>>Will re-test remotely (including Target Acquisition) within 6 weeks
Testing and results are very positive!
K:\cos\coslogo1.jpg
Keyes - 22 January 2003
Slide 3 of  6
New Launch Date Impacts
Ground System Development
SMOV4-related
>>SMGT now planned for late June, 2004
>>Special commanding definition now required by September, 2003
COWG will establish requirements in spring
>>Requirements (other activities e.g., on-orbit calibration) : definition Sep-Nov 2003
Revised STScI Phase Development Plan
>>Includes new work items and updates
K:\cos\coslogo1.jpg
Keyes - 22 January 2003
Slide 4 of  6
COS Phase Development Plan(Rev 8, 01/06/03)
Phase (1/1/00 – 6/30/00)Phase (1/1/00 – 6/30/00)
vMacro DevelopmentvMacro Development
vReconfigurationsvReconfigurations
Phase (7/1/00 – 12/31/00)Phase (7/1/00 – 12/31/00)
vNUV Timetag Mode DarksvNUV Timetag Mode Darks
vFUV Timetag Mode DarksvFUV Timetag Mode Darks
Phase (1/1/01 – 6/30/01)Phase (1/1/01 – 6/30/01)
vFUV NUV Accumulation Science ExposuresvFUV NUV Accumulation Science Exposures
vFUV NUV Target Acquisition ExposuresvFUV NUV Target Acquisition Exposures
vFUV NUV Target Peakup ExposuresvFUV NUV Target Peakup Exposures
Phase (7/1/01 – 12/31/01)Phase (7/1/01 – 12/31/01)
vAperture Alignment ExposuresvAperture Alignment Exposures
vOSM1 Focus Alignment ExposuresvOSM1 Focus Alignment Exposures
vOSM1 Rotation Alignment ExposuresvOSM1 Rotation Alignment Exposures
vOSM2 Rotation Alignment ExposuresvOSM2 Rotation Alignment Exposures
vFUV NUV FP Split ExposuresvFUV NUV FP Split Exposures
Phase (1/1/02 – 6/30/02)Phase (1/1/02 – 6/30/02)
vFUV NUV GO Wavelength Calibration ExposuresvFUV NUV GO Wavelength Calibration Exposures
vFUV NUV Flat Field Lamp Calibration ExposuresvFUV NUV Flat Field Lamp Calibration Exposures
vFUV NUV Automatic Wavelength Calibration ExposuresvFUV NUV Automatic Wavelength Calibration Exposures
vSAA ContoursvSAA Contours
Phase (7/1/02 – 12/31/02)Phase (7/1/02 – 12/31/02)
vFUV NUV BOP Target ScreeningvFUV NUV BOP Target Screening
Phase (1/1/03 – 6/30/03)Phase (1/1/03 – 6/30/03)
vFUV NUV Flat Field Lamp ReworkvFUV NUV Flat Field Lamp Rework
vCoordinated ParallelsvCoordinated Parallels
Phase (7/1/03 – 12/31/03)Phase (7/1/03 – 12/31/03)
vOSM Overheating AvoidancevOSM Overheating Avoidance
vSMGT PreparationsvSMGT Preparations
vSMOV Special CommandingvSMOV Special Commanding
vFUV NUV Anomalous RecoveryvFUV NUV Anomalous Recovery
vFUV NUV Initial Turn-onvFUV NUV Initial Turn-on
Phase (1/1/04 – 6/30/04)Phase (1/1/04 – 6/30/04)
vTRANS ovratalstart, ovratalendvTRANS ovratalstart, ovratalend
Phase 10 (7/1/04 – 12/31/04)Phase 10 (7/1/04 – 12/31/04)
vFUV NUV Lifetime AdjustmentsvFUV NUV Lifetime Adjustments
\\squeaker\Office2000Premium\PFiles\Common\MSShared\Clipart\themes1\bullets\bd21300_.gif
\\squeaker\Office2000Premium\PFiles\Common\MSShared\Clipart\themes1\bullets\bd21300_.gif
K:\cos\coslogo1.jpg
Keyes - 22 January 2003
Slide 5 of  6
STScI Calibration Pipeline Status
OPUSOPUS
Successful testing with integrated SI data (from N2 purge)
Testing against latest DM-06 and Target Acquisition data suite planned
COS Keyword Dictionary in preparation
CALCOSCALCOS
Most modules are now complete
Successful testing with integrated SI data (from N2 purge)
Draft of ICD-47 is being reviewed
K:\cos\coslogo1.jpg
Keyes - 22 January 2003
Slide 6 of  6
STScI Thermal-Vac Support
STScI Coordination with IDT (STScI lead:  Sembach)STScI Coordination with IDT (STScI lead:  Sembach)
OPUS support of Thermal-VacOPUS support of Thermal-Vac
MOU requires STScI to deliver T-Vac version of OPUS two months inadvance of T-Vac – on-track
>>Require test (simulator) target acquisition images 2-4 weeks in advance of thisdate if OPUS delivery is to include target acquisition functionality
>>Minor T-V logistics issues being worked (e.g., additional k/w)
>>Coordination ongoing with IDT – all nominal
STScI Staffing Support at T-VacSTScI Staffing Support at T-Vac