Groundwater Protection InitiativeAnd Other Issues Of Interest
George Oliver
RETS/REMP Conference
Charlotte, NC
June 23, 2008
NEI-logo-white
NEI-logo-white
2
NEI Groundwater Protection Initiative
Nuclear Generating Unit Issues 2005-2006
Indian Point, Braidwood…..
NRC Also Formed “The Liquid RadioactiveRelease Lesson Learned Task Force
Report September 1, 2006
26 Recommendations
Not A Health And Safety Issue
It Was An Issue About Communications AndPublic Perception (Transparency)
NEI-logo-white
NEI-logo-white
3
NEI Groundwater Protection Initiative
Applies To All Nuclear Generating Plants
Technical Groundwater Protection Requirements
Hydrogeology  And Geology
Risk Assessment
Monitoring
Remediation And Records
Communication Of Leaks/Spills And Monitoring
Program Oversight
NEI-logo-white
NEI-logo-white
4
NEI Groundwater Protection Initiative
What Has Happened In The Last Year?
NEI 07-07 Guidance Document Issued7-31-2007
One Year Period For Implementation
NRC Public Meeting 9-27-2007
EPRI Groundwater Protection Guidelines Issued11-2007
NRC Public Meeting 2-5-2008
NRC RIS 2008-03 Return & Reuse of PreviouslyDischarged Radioactive Effluents
NEI-logo-white
NEI-logo-white
5
NEI Groundwater Protection Initiative
What Has Happened In The Last Year?
NRC Issues TI 2515/173
“GWPI Implementation Assessment Issued”
 5-29-2008
Coming Attractions
NRC Begins Assessment 9-1-2008
GWPI Self Assessments (One Year AfterImplementation)
NEI Sponsored Peer Assessments
EPRI/NEI Groundwater Protection Workshop
September 23-25, 2008 - Augusta GA
NEI-logo-white
NEI-logo-white
6
Additional Issues of Interest Decommissioning Planning Rules
Decommissioning Planning Rulemaking
Federal Register Notice 1-22-2008
Very Extensive Rulemaking
10 CFR Parts 20, 30, 50, 70, 72
Financial And Monitoring Guidance
Comments Submitted 5-8-2006
NEI & 12 Nuclear Utilities
32 Sets of Comments 21 From Industry
NEI Decommissioning Taskforce
NEI-logo-white
NEI-logo-white
7
Additional Issues of Interest Decommissioning Planning Rules
The Nuclear Industry Shares The NRC Goal OfPreventing Legacy Sites
We Do Not Believe The Proposed Rules AreRequired To Prevent Future Legacy Sites
Any Health And Safety Benefits Do Not Justify TheBurden Created By The Rules
We Also Believe The Proposed Rules Are ABackfit
The Nuclear Industry Is Prepared To Work WithNRC To Improve The Regulatory Process RelatedTo Decommissioning
NEI-logo-white
NEI-logo-white
8
Additional Issues of Interest Decommissioning Planning Rules
Rules Provide For Adjustment of FinancialAssurances Based On Soil Or GroundwaterContamination
Rules Provide For Subsurface EvaluationsThat May Generate Extensive OperationalCharacterization & Remediation Based OnDecommissioning Criteria
NEI-logo-white
NEI-logo-white
9
Additional Issues of Interest Decommissioning Planning Rules
MARSSIM Is Being Established ForOperational Monitoring Preformed UnderThis Proposed Rule
New Requirements For Leak DetectionAnd Containment
May Require Extensive GroundwaterModeling Even With No SubsurfaceContamination
NEI-logo-white
NEI-logo-white
10
Additional Issues of Interest Decommissioning Planning Rules
Use Of The GWPI CommunicationThresholds (100 Gal Spill) To DefineSignificant For Decommissioning Records
Future Activity
NRC Is Reviewing The Comments From ThePublic Comment Period
A NRC Stakeholder Workshop IsAnticipated Later This Year
NEI-logo-white
NEI-logo-white
11
Additional Issues of InterestRegulatory Guide 4.21
NEC Issues Regulatory Guide 4.21
June 6, 2008 “Minimization ofContamination and Radioactive WasteGeneration: Life Cycle Planning”
AKA 20.1406 & DG 4012
Industry Contributions To Regulatory Guide
Template To Be Developed