Chapter 5
Initiating and PlanningSystems Development Projects
Modern Systems Analysisand DesignFourth Edition Jeffrey A. HofferJoey F. GeorgeJoseph S. Valacich
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-2
Learning Objectives
Describe steps involved in project initiation and planning.
Explain the need for and contents of Statement of Workand Baseline Project Plan.
List and describe methods for assessing projectfeasibility.
Describe tangible vs. intangible costs and benefits, andone-time vs. recurring costs and benefits.
Perform cost-benefit analysis, and understand time valueof money, present value, discount rate, return oninvestment, and break-even analysis.
Describe rules for evaluating technical risk of systemsdevelopment projects.
Describe activities and roles of structured walkthroughs.
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-3
Project Initiation and Planning
FIG05_01
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-4
Project Initiation Tasks
Establish:
Initiation team
Relationship with customer
Project initiation plan
Management procedures
Project management environment
Project workbook
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-5
Project Planning Tasks
Describe project scope, alternatives, feasibility.
Divide project into tasks.
Estimate resource requirements and create resourceplan.
Develop preliminary schedule.
Develop communication plan.
Determine standards and procedures.
Identify and assess risk.
Create preliminary budget.
Develop a statement of work.
Set baseline project plan.
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-6
Deliverables and Outcomes
Business Case
Justification for an information system,expressed as tangible and intangible costsand benefits (preliminary budget), andtechnical/organizational feasibility
Baseline Project Plan (BPP)
Statement of Work (SOW)
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-7
Statement of Work(SOW) is a “contract”between the IS staffand the customerregardingdeliverables and timeestimates for asystem developmentproject.
FIG05_02
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-8
System ServiceRequest (SSR) is aform requestingdevelopment ormaintenance of aninformation system. Itincludes the contactperson, a problemstatement, a servicerequest statement, andliaison contactinformation.
FIG05_03
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-9
Assessing Project Feasibility
Economic feasibility
Technical feasibility
Operational feasibility
Schedule feasibility
Legal and contractual feasibility
Political feasibility
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-10
Economic Feasibility
Cost-benefit analysis: identify all thefinancial benefits and costs associatedwith a project
Tangible vs. intangible benefits
Tangible vs. intangible costs
One-time vs. recurring costs
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-11
Tangible Benefits
FIG05_04
Benefitsthat can bemeasuredin dollarsand withcertainty
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-12
Benefits that cannot easily be measured in dollars or with certainty
TBL05_03
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-13
Types of Costs
Tangible: can be measured in dollars andwith certainty
Intangible: cannot easily be measured indollars or with certainty
One-time: a cost associated with project start-up and development or systems start-up
Recurring: a cost associated with ongoingevolution and use of a system
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-14
Possible IS Project Costs
Procurement
Consulting, equipment, site preparation, capital,management time
Start-up
Operating systems, communications installation,personnel hiring, organizational disruption
Project-related
Application software, software modification,personnel overhead, training, data analysis,documentation
Operating
System maintenance, rental, asset depreciation,operation and planning
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-15
One-time Costs
FIG05_05
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-16
FIG05_06
Recurring Costs
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-17
Three Financial Measurementsfor Economic Feasibility
Net Present Value (NPV)
Use discount rate to determine presentvalue of cash outlays and receipts
Return on Investment (ROI)
Ratio of cash receipts to cash outlays
Break-Even Analysis (BEA)
Amount of time required for cumulativecash flow to equal initial and ongoinginvestment
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-18
Definitions of Terms
Present value: current value of a futurecash flow
Discount rate: rate of return used tocalculate the present value of futurecash flows
Time value of money (TVM): comparingpresent cash outlays to future expectedreturns
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-19
Net Present Value
PVn = present value of Y dollars n years fromnow based on a discount rate of i.
NPV = sum of PVs across years.
Calculates time value of money.
CAP1
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-20
Break-Even Analysis
CAP4
FIG05_08
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-21
Technical Feasibility
Assessing the organization’s ability toconstruct the proposed system
Takes into account various project riskfactors
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-22
Project Risk Factors
Project size
Team size, organizational departments, project duration,programming effort
Project structure
New vs. renovated system, resulting organizational changes,management commitment, user perceptions
Development group
Familiarity with platform, software, development method,application area, development of similar systems
User group
Familiarity with IS development process, application area, useof similar systems
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-23
High technical familiarity mitigates risk due to project sizeand structure. Low familiarity increases risk.
FIG05_09
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-24
Other Feasibility Concerns
Operational
Does the proposed system solve problems or take advantage ofopportunities?
Did it come from ISP?
Large impact on organization’s structure and procedures -- riskier
Schedule
Can the project time frame and completion dates meet organizationaldeadlines?
Government deadline, business cycle, competitor deadline
Vacations and holidays
“Rough cut” during this phase
Trade-offs – development environments, personnel
Legal and Contractual
What are legal and contractual ramifications of the proposed systemdevelopment project?
Software licensing, copyrights, ownership of software, etc.
Political
How do key stakeholders view the proposed system?
Impacts distribution of power?
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-25
Baseline Project Plan(BPP) is adocument intendedprimarily to guidethe developmentteam.
Sections:
1)Introduction
2)System description
3)Feasibilityassessment
4)Managementissues
FIG05_10
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-26
Project Scopestatement is partof the BPPintroduction.
Sections:
1)Problem statement
2)Project objectives
3)Project description
4)Business benefits
5)Deliverables
6)Expected duration
FIG05_11
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-27
Factors in Determining Scope
Organizational units affected by newsystem
Current systems that will interact with orchange because of new system
People who are affected by new system
Range of potential system capabilities
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-28
Diagram Depiction of Project Scope
FIG05_12
Context level is a top level data flow diagram. Data flow diagramsare covered in Chapter 7.
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-29
Structured Walkthroughs
A peer-group review of any product createdduring the system development process
Roles: coordinator, presenter, user,secretary, standard-bearer, maintenanceoracle
Can be applied to BPP, systemspecifications, logical and physical designs,program code, test procedures, manuals anddocumentation
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-30
Structuredwalkthroughform
FIG05_13
© 2005 by Prentice Hall© 2005 by Prentice Hall
5-31
Summary
In this chapter you learned how to:
Describe steps involved in project initiation and planning.
Explain the need for and contents of Statement of Work andBaseline Project Plan.
List and describe methods for assessing project feasibility.
Describe tangible vs. intangible costs and benefits, and one-time vs. recurring costs and benefits.
Perform cost-benefit analysis, and understand time value ofmoney, present value, discount rate, return on investment,and break-even analysis.
Describe rules for evaluating technical risk of systemsdevelopment projects.
Describe activities and roles of structured walkthroughs.