PCWG
9th Meeting:  12 December 2014 - Glasgow
Introduction, Agenda and Review of Actions
Motivation: to agree the 2015 roadmap for the PCWG.
Morning Session:  09:30 – 13:00
09:30 - 09:40 “Welcome”, Ralph Torr (ORE Catapult – Event Host)
09:40 - 10:00 PCWG Status & Action Update  – Peter Stuart (RES)
10:00 - 10:30 Round Robin 4 Results Overview and Discussion
10:30 - 11:30 2015 Road Map Discussion (All):
Discussion of proposed PCWG data sharing initiative.
Survey results
Presentation of draft roadmap
Group Exercise
11.30 – 11.45 Coffee Break
11:45 - 13:00 Road Map Discussion Continue (All)
13.00 – 14.00 Lunch
14:00 - 15:00 Afternoon Presentations Session Part 1
14:00 – 14:15 Richard Whiting DNV GL: “Modelling Type B effects in the 4th Quadrantusing Bladed)
14:15 – 14:30 Stuart Baylis, Prevailing “A Novel Method for Improving TurbinePerformance Predictions by Considering the Frequency Distribution of Shear”
14:30 – 14:45 “Redefinition of Power Curves: Electric vs. Kinetic Power”, Erik TüxenDNV GL.
14:45 – 15:00 Presentation Discussion
15:15 - 16:00 Afternoon Presentations Session Part 2: LiDARs
15:15 – 15:30 Lidar observations of the compression zone and capabilities as aturbulence instrument”, Peter Clive Sgurr
15:30 – 15:45 Michael Harris, ZephIR, "ANALYSIS OF REAL WORLD TURBINEPERFORMANCE USING FORWARD-FACING NACELLE LIDAR".
15:45 – 16:00 Presentation Discussion
Discussion Session: 16.00 – 16.45
Finalisation of turbulence correction consensus analysis and associateddocumentation.
Review of Proposed Round Robin 5: “Power Deviation Matrices”
Afternoon Wrap Up: 16.45 – 17.00
Venue for next meeting
Public distribution of presentations and minutes
Review of Previous Actions
Develop glossary of terms.
Perform round robin exercise for Veer term of REWS method using Dataset 3.
Improve consensus analysis for turbulence renormalisation method makingcalculation steps clearer e.g. flow charts.
Publically distribute Inner-Outer range concept document.
Identify and distribute additional validation datasets:
Galion dataset from SSE
Dedicate portion of next meeting to Type B effects.
Actions from Dec 2013 Meeting
Complete Rotor Equivalent Wind Speed (Veer) Exercise (revised deadline 27th ofJune)
Develop Guideline Document on the Presentation of Power Curve Information
Develop Guideline Document on the Application of the Turbulence RenormalisationMethod
Engage with research institutions to test Type B hypotheses using ‘open-source’rotors.
Develop proof of concept for the ‘Black Box Model’ approach.
Release python implementation of consensus analysis as open source.
Investigate the possibility of hosting a PCWG event in the US.
Publicise meeting via AWEA
Release 4th RR exercise
1st April 2014
Improve documentation of consensus analysis of turbulence correction (flow charts)
Add user interface to Open Source Tool
Publish Road Map for PCWG 2015 activities.
Complete 4th Round Robin in advance of December Meeting
Arrange a Round Robin on Power Deviation Matrix Method
Arrange a Round Robin on Rotor Equivalent Wind Speed considering inflow.
Explore enhanced data sharing exercise (possibly utilising open source tool).
Revisit proposal to use Open Source Rotor to investigate “Type B” performanceeffects.
September 2014
The members present agreed that the PCWG should continue its activities for 2015. Aroadmap will be prepared detailing the planned objectives and activities for 2015.
The IEC 61400-12-1 committee and PCWG should aim to hold a further joint meetingin 2015 (timed with an existing 61400-12-1 meeting to minimise travel).
A manufacturer PCWG member will investigate supplying climate/site specific powercurves for forthcoming the round robin.
PCWG to add action to 2015 roadmap to develop data specification for climate/sitespecific power curves. This should detail both the input data required by amanufacturer to generate a site specific power curve and the output data required bya developer/consultant in order to do their analysis.
PCWG to explore establishing a named liaison between the PCWG and the IEC 61400-15 (Resource Assessment) standard committee.
PCWG to explore preparing a document that would outline the benefits ofmanufacturers supplying power deviation matrices on an informative basis.
PCWG to conduct round robin on application of power deviation method.
PCWG members to explore release of additional datasets to the PCWG.
PCWG to explore adding IEC uncertainty calculation to PCWG open source tool.
October Meeting Key Outcomes