Aftermath of the INES-3 Incidentat Paks NPPon 10th April, 2003.
Lajos Vöröss
Hungarian Atomic Energy Authority
7th Annual Meeting of NERS
IAEA, Vienna, 23-24, September 2004.
2
3
 Main Tasks to Perform
After having stabilised the situation inside thereactor hall there have been two main tasksto perform:
1. Recovery of service shaft No.1 of Unit 2. (SS) where theincident occurred
2. Restart of Unit 2. as soon as possible
 
 
 
 
 
4
 - Recovery project and team established at Paks NPP
 - Tendering process won by Russian consortium led byTVEL; FRAMATOM had bidden as well
 - 6-8 months preparatory, 2-3 months implement phasesplanned, excluded licensing time - significant delay now
 - Special tools for manual removal of debris are to beused
 - Manipulation is to be carried out from a movableplatform placed above the cleaning tank
 - Some experiments to clarify behaviour of debris forplanned removal actions performed
 
Recovery of SS
5
Recovery outline – FRA/ GER
crane
air filter
manipulator
working rod
suction
control panel
container
cleaning tank
versions
removal of the cleaningtank and fuel in one step(dismissed later –difficult, does not givefinal solution)
removal of the cleaningtank and fuel in partswith clips, bending tools,manipulators, vacuumsoakers, cutters
6
Recovery outline –RUS
shell
container
different
- water level,
- boron
  concent-
  ration,
- contami-
  nation
ГИ ВНИПИЭТ
ГП НИКИМТ
ПО Маяк
НПФ Сосны
structure
winner
mostlymanual
removal
moving
platform
7
 
Separation of SS from spent fuel pond and from other
   systems of Unit 2.became necessary
- Autonomous cooling device and emergency boron
   injection system for SS have been installed
- Mobile water cleaning device (NURES,Finland) was used
  to clean the water especially from the uranium and trans-uranium isotopes
      Recovery of SS (cont’d)
8
Recovery of SS (cont’d)
 - Reliable neutron flux and boron concentrationmeasurement in SS installed
 - Increased radwaste storage capacity constructed
 - Free positions made available for capsules/cartridgescontaining debris in spent fuel pool
 - Preparatory actions for regulatory licensing process
    - regulatory requirements for recovery developed
    - review and assessment in large number ofmodifications and fabrication of equipmentperformed
 
9
 Restart of Unit 2.
- After long-term shut-down status with intact main equipmentbut contaminated by uranium and trans-uranium isotopes -special cleaning was necessary (completed)
 - Interrupted refuelling and maintenance occurred during theincident
 - RPV used as temporary storage tank of spent fuelassemblies
 - Low enrichment fresh FE supply and rearrangement of spentfuel pool became necessary
 - Reuse of cleaned spent fuel assemblies is limited
10
     Restart of Unit 2. (cont’d)
 - Conception for short term operation cycle developed
   - refuelling and yearly maintenance  completed
    - suitable core for operation during the preparatoryphase of the recovery is possible (about 4 monthslong)
    - regulatory requirements for restart/operation phasesdeveloped, licence given on 16. July, 2004.
    - nearly full power operation started on 02 Sept. 2004.
-  Keen interest from media and public follows
 
11
 International Assistance
- IAEA - two international missions provided at Paks NPP
- GAN (Russian Regulator) - on basis of contractualarrangement, focuses to review QA of Russiancontractors
 - US NRC/IAEA - gives advice to review conditions ofrestart of Unit 2.
 
NOTE: In spite of the incident, lifetime extension andpower uprating of the units are still insisted on